Project Timelines

Consultation Process
(January – June 2023)

Informal pre-application discussions with Birmingham City Council

January - March 2023

Formal pre-application process with Birmingham City Council

April - July 2023

Engagement with key consultees and stakeholders

March 2023 – Ongoing

Public Exhibition and Consultation Events

April 2023

Planning Process
(January 2023 – June 2024)

Design development

Summer 2022 – Ongoing

Informal pre-application discussions with Birmingham City Council

January - March 2023

Formal pre-application process with Birmingham City Council

April - July 2023

Completion of technical work

January 2023 – Ongoing

Submission of Planning Application

August 2023

Determination Period

August - November 2023

Resolution of Grant Planning Permission

November 2023

Finalise Section 106 Agreement
November - December 2023

Discharge of Planning Conditions

December 2023 - Mid 2024

Construction Process
(July 2024 – March 2027)

Demolition / structural / foundations works

Summer 2024 – Spring 2025

Building new structure

Spring 2025 – Winter 2025

Installing new facades

Autumn 2025 – Spring 2026

Internal fitting out

Spring 2026 – Winter 2026

External Space Works

Summer 2026 – Winter 2026

Completion

Spring 2027