Project Timelines
Consultation Process
(January – June 2023)
Informal pre-application discussions with Birmingham City Council
January - March 2023
Formal pre-application process with Birmingham City Council
April - July 2023
Engagement with key consultees and stakeholders
March 2023 – Ongoing
Public Exhibition and Consultation Events
April 2023
Planning Process
(January 2023 – June 2024)
Design development
Summer 2022 – Ongoing
Informal pre-application discussions with Birmingham City Council
January - March 2023
Formal pre-application process with Birmingham City Council
April - July 2023
Completion of technical work
January 2023 – Ongoing
Submission of Planning Application
August 2023
Determination Period
August - November 2023
Resolution of Grant Planning Permission
November 2023
Finalise Section 106 Agreement
November - December 2023
Discharge of Planning Conditions
December 2023 - Mid 2024
Construction Process
(July 2024 – March 2027)
Demolition / structural / foundations works
Summer 2024 – Spring 2025
Building new structure
Spring 2025 – Winter 2025
Installing new facades
Autumn 2025 – Spring 2026
Internal fitting out
Spring 2026 – Winter 2026
External Space Works
Summer 2026 – Winter 2026
Completion
Spring 2027